PSDP Services in Ireland

Project Supervisor for the Design Process: the statutory appointment under the Construction Regulations 2013

  • Fixed-fee quote within one working day
  • Based in Co. Wicklow, working across Leinster
  • Over 25 years of construction safety experience

What is a PSDP?

The Project Supervisor for the Design Process (PSDP) is a statutory appointment required under the Safety, Health and Welfare at Work (Construction) Regulations 2013. The key role of the PSDP is to ensure co-ordination of the work of designers throughout the project.

When do you need a PSDP?

Under Regulation 6 of the Safety, Health and Welfare at Work (Construction) Regulations 2013, the client must appoint a PSDP, in writing, at or before the start of the design process, if any one of these applies:

  • the work involves a particular risk (for example work at height made worse by other factors, deep excavations, work near high-voltage lines, or asbestos);
  • more than one contractor is involved; or
  • the construction work is planned to last longer than 30 working days, or is scheduled to exceed 500 person days.

So a short job with two or more contractors needs a PSDP just as a long single-contractor job does. The 30 working day / 500 person day level is also the point at which the client must notify the HSA (form AF1). A PSCS must be appointed on the same basis, before construction starts.

Sources: HSA guidance for clients | S.I. 291/2013, Regulation 6

What we do as your PSDP

  • Identify hazards arising from the design or from the technical, organisational, planning or time-related aspects of the project
  • Where possible, eliminate those hazards or reduce the risk
  • Communicate necessary control measures, design assumptions or remaining risks to the PSCS so they can be dealt with in the Safety and Health Plan
  • Ensure that the work of designers is co-ordinated to ensure safety, and organise co-operation between designers
  • Prepare a written Safety and Health Plan for any notifiable project and deliver it to the client prior to tender
  • Prepare a Safety File for the completed structure and give it to the client
  • Notify the HSA and client of non-compliance with any written directions issued
Safety Check PSDP Services — construction site

How it works

  1. You send us the project details.
  2. We send you a fixed-fee quote within one working day.
  3. You appoint us in writing, and we confirm acceptance in writing, at or before the start of design work.
  4. We coordinate the designers, issue the Preliminary Safety and Health Plan and hand over the Safety File on completion.

What you receive

  • Appointment confirmation
  • Preliminary Safety and Health Plan
  • designer-coordination record
  • Safety File on completion

PSDP or PSCS?

PSDPPSCS
Design stageConstruction stage
Appointed at or before the start of designAppointed before construction starts

Need a PSCS as well? See our PSCS services

Read the full explanation

Where we work

We also work in Longford, Westmeath and Wexford.

Frequently Asked Questions

What does PSDP stand for?

Project Supervisor for the Design Process.

What is the difference between a PSDP and a PSCS?

The PSDP (Project Supervisor for the Design Process) works during the design phase, coordinating designer safety and preparing the Safety and Health Plan. The PSCS (Project Supervisor for the Construction Stage) works during construction, coordinating contractor safety and implementing the Safety and Health Plan.

When does a project need a PSDP?

A project needs a PSDP if the work involves a particular risk (for example work at height made worse by other factors, deep excavations, work near high-voltage lines, or asbestos), more than one contractor is involved, or the construction work is planned to last longer than 30 working days or exceed 500 person days.

Who appoints the PSDP, and when?

The client, in writing, at or before the start of the design process; the PSDP must accept in writing.

Who can act as a PSDP?

A PSDP or PSCS must be a competent person with the knowledge, training, and experience to carry out the role. This typically means a safety consultant, project manager, architect, or engineer with relevant qualifications and practical construction experience. The HSA does not maintain a register of approved PSDP or PSCS practitioners.

What is the Safety and Health Plan?

The Safety and Health Plan is a document that sets out how safety will be managed during construction. The PSDP prepares a preliminary Safety and Health Plan during design, based on the design-stage hazards and risks. The PSCS then develops this into the full Safety and Health Plan before construction starts, incorporating site-specific information, contractor details, and construction-stage hazards.

What is the Safety File?

The Safety File is a document prepared by the PSDP (with information provided by the PSCS) that contains information relevant to the safety of workers who will work on the structure in the future. It is handed over to the client on project completion.

Do I need to notify the HSA?

The client notifies the HSA on form AF1, before the design process begins, where the construction work is planned to last longer than 30 working days or exceed 500 person days. The PSCS notifies the HSA on form AF2 before construction starts. A shorter project can still need a PSDP and PSCS but no HSA notification.

HSA construction notification guide

How much does a PSDP cost?

It depends on the size and complexity of the project. Request a quote and we will send you a fixed-fee quote within one working day.